Question:

‘RAVL’ is a company manufacturing LED bulbs. To ensure efficiency in production, the workers are given monthly targets. For the month of October 2025, the workers were given a target to produce 8,000 bulbs. At the end of the month, it was found that actual production was only 6,000 bulbs. After investigation, it was found that the target was not met due to shortage of trained workers. To resolve the problem, the Production Manager arranged training programmes for workers and also hired additional workers.

Which step of the controlling process was followed by the Production Manager to resolve the problem of shortage of trained workers ?

Show Hint

Training workers and hiring more is action taken after the cause of the shortfall was found. That is the last step, taking corrective action.
Updated On: Oct 26, 2026
  • Setting performance standards
  • Measurement of actual performance
  • Comparing actual performance with standards
  • Taking corrective action
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Step 1: Read the problem in the case:
The target was 8,000 bulbs but only 6,000 were made.
The cause was found to be a shortage of trained workers. The manager then arranged training and hired more workers.

Step 2: Identify the step:
Arranging training and hiring workers is action taken to remove the cause of the deviation.
That is the step of taking corrective action, which is option (D).

Step 3: Why the other options are wrong:
(A) Setting performance standards: the standard of 8,000 bulbs was already fixed before the work began.
(B) Measurement of actual performance: this was done when the output of 6,000 bulbs was recorded.
(C) Comparing actual performance with standards: this was done when 6,000 was set against 8,000 and a shortfall was seen.

Final Answer:
Training and hiring workers are corrective action, so option (D) is correct.