Step 1: Understanding the concept:
The sentence describes a plan about a project that lists objectives, policies, procedures, rules, tasks, resources and a budget.
We must pick the type of plan that is defined in this way.
Step 2: Recall the definition:
A programme is a detailed statement about a project which outlines the objectives, policies, procedures, rules, tasks, human and physical resources required and the budget to implement any course of action.
So the given line is the definition of programme.
Step 3: Why option (C) Programme is correct:
The blank-filled sentence matches the definition of programme word for word.
A programme brings many other plans together for one project.
Step 4: Why option (A) Rule is wrong:
A rule is a specific statement telling what is to be done or not to be done in a situation.
It does not cover tasks, resources or budget.
Step 5: Why option (B) Strategy is wrong:
A strategy is a comprehensive plan for achieving the long-term objectives of the organisation, keeping the environment in mind.
It is a broad plan and not a detailed statement for a project.
Step 6: Why option (D) Procedure is wrong:
A procedure is a series of routine steps arranged in order for doing a job.
It does not include objectives, budget or resources of a whole project.
Final Answer:
The detailed project statement is a programme. The correct option is (C).