Question:

‘GEO Builders’ were to complete a housing project by December 2024 and hand over the flats to the buyers. Due to excessive heat in the month of May and June 2024, the work slowed down and the project was getting delayed. The firm, in order to complete the project on time, hired more workers through a contractor and asked all the workers to work overtime. Due to the above measures taken by the management, the project was completed on time but the cost of building the flats increased by 10%.

Identify the correct option.

‘GEO Builders’ were :

Show Hint

The project ended on time (effective) but the cost rose 10 percent (not efficient).
Updated On: Nov 11, 2026
  • Efficient but not effective
  • Effective but not efficient
  • Neither effective nor efficient
  • Effective as well as efficient
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Recall the two terms:
Effectiveness means completing the given task on time. It is about doing the right thing. It compares the result with the target.
Efficiency means doing the task correctly with the least cost. It is about doing the thing right. It compares the result with the resources used.

Step 2: Test effectiveness of GEO Builders:
The target was to finish the project by December 2024 and hand over the flats. The project was completed on time.
So the target was met, and the firm was effective.

Step 3: Test efficiency of GEO Builders:
To beat the delay, the firm hired more workers through a contractor and asked all workers to work overtime.
As a result, the cost of building the flats increased by 10%. More cost for the same flats means the resources were not used in the best way.
So the firm was not efficient.

Step 4: Check each option:
(A) Efficient but not effective is the opposite of what happened, so it is wrong.
(B) Effective but not efficient is right, since the work was done on time but at a higher cost.
(C) Neither effective nor efficient is wrong, because the project target was met.
(D) Effective as well as efficient is wrong, because the cost went up by 10%.

Final Answer:
GEO Builders were effective but not efficient, which is option (B).
Was this answer helpful?
0
0

Top CBSE CLASS XII Nature and Significance of Management Questions

View More Questions