‘Cosy Garments’ started the manufacturing of jackets in September, 2025. They expected a rise in the demand for jackets during the winter season. To handle the increased workload, the Production Manager estimated the number of workers required during peak production days and planned accordingly.

The type of plan highlighted in the above case is :

Show Hint

The manager estimates the number of workers needed for the peak season. A plan that states expected needs in numbers for a period is a budget.
Updated On: Oct 26, 2026
  • Budget
  • Policy
  • Method
  • Objective
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Understanding the case:
Cosy Garments expects more demand for jackets in winter.
The Production Manager estimates the number of workers needed on peak days and plans for it.

Step 2: Recall the types of plans:
Objective is the end result to be reached. Policy is a general guide for thinking. Method is the way of doing one task.
A budget is a statement of expected results in numerical terms for a given period. It is an estimate of the needs in figures.

Step 3: Why option (A) Budget is correct:
In the case, the manager estimates the number of workers required. This is a forecast in numbers for the coming peak period.
A budget is exactly such a numerical plan, which can be about workers, money, material or output.

Step 4: Why option (B) Policy is wrong:
A policy is a general statement that guides decision-making. It has no numbers or estimates.
The case does not show any guidance for thinking, so it is not a policy.

Step 5: Why option (C) Method is wrong:
A method is the prescribed way in which a single task is to be done.
The manager is not describing how to do a task but how many workers are needed, so it is not a method.

Step 6: Why option (D) Objective is wrong:
An objective is the desired end result or target of the organisation.
Here the firm is not stating a goal but estimating the manpower, so it is not an objective.

Final Answer:
The estimate of workers for the peak season in numerical form is a budget. The correct option is (A).
Was this answer helpful?