Step 1: Understanding the Concept:
This question tests knowledge of the proper sequence of building construction activities.
Step 2: Detailed Explanation:
Site Selection (C):
First step - Identify and select the location for construction.
This considers factors like soil type, climate, infrastructure, and legal clearances.
Floor Plan (D):
Second step - Prepare the architectural plan and layout.
This determines the design, dimensions, and arrangement of rooms.
Foundation (B):
Third step - Construct the foundation of the building.
This transfers the load of the building to the ground.
Construction of Walls (F):
Fourth step - Build the walls according to the floor plan.
Walls provide support and enclose the space.
Construction of Roof (E):
Fifth step - Construct the roof over the walls.
The roof protects the building from weather elements.
Construction of Floor (A):
Sixth step - Build the floor finishes.
This is typically done after the walls and roof are complete.
Step 3: Final Answer:
Thus, the correct sequence is C, D, B, F, E, A, which corresponds to option (C).