Question:

Arrange the following steps for applying the critical path method in the correct sequence :
A. Identification of all activities that the project require.
B. Network Diagram Construction
C. Critical Path Determination
D. Activity Duration Estimation
Choose the correct answer from the options given below :

Show Hint

Any delay in an activity on the "Critical Path" will directly result in a delay of the entire project completion date.
Updated On: Oct 3, 2026
  • A, D, B, C
  • A, B, D, C
  • D, A, B, C
  • B, A, D, C
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Understanding the Question:

• Arrange the steps of the Critical Path Method in order.

Step 2: Detailed Explanation:


• First, identify all activities the project requires (A).

• Second, estimate the duration of each activity (D).

• Third, construct the network diagram showing the logical dependencies (B).

• Finally, determine the critical path (C).

• Sequence: A, D, B, C.

Step 3: Final Answer:

The correct option is (A) A, D, B, C.
Was this answer helpful?
0
0

Top CUET PG Compass Surveying and Theodolite Questions