Question:

Identify the correct sequence of steps in the process of planning.
A. Setting objectives
B. Identifying alternatives courses of action
C. Developing premises
D. Selecting an alternative
E. Evaluating alternative courses of action
Choose the correct answer from the options given below :

Updated On: Feb 26, 2026
  • A, C, D, B, E
  • C, D, B, A, E
  • A, C, B, E, D
  • D, E, B, A, C
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct option is (C) :A, C, B, E, D.