Question:

What is the correct sequence of assembly operation of peg-in-hole assembly? A. Hole crossing
B. Two-point contact
C. Approach
D. One-point contact

Show Hint

Assembly progresses from free motion → single contact → constrained insertion.
Updated On: May 22, 2026
  • A, C, B, D
  • A, B, C, D
  • C, A, D, B
  • C, D, A, B
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Concept: Peg-in-hole assembly is a classical problem in robotics and manufacturing involving constrained motion and contact transitions.

Step 1: Understand the stages.

The operation progresses through:
• Free motion (approach)
• Initial contact
• Increased constraint contact
• Full insertion

Step 2: First stage — Approach (C).


• Peg moves freely towards hole
• No contact exists

Step 3: Second stage — One-point contact (D).


• Peg touches rim of hole at one point
• Initial constraint begins

Step 4: Third stage — Hole crossing (A).


• Peg begins entering hole
• Alignment improves

Step 5: Fourth stage — Two-point contact (B).


• Peg contacts hole at two points
• Fully constrained during insertion

Step 6: Final sequence.

\[ C \rightarrow D \rightarrow A \rightarrow B \] Final Answer: \[ \boxed{C, D, A, B} \]
Was this answer helpful?
0
0

Top CUET PG Mechanical Engineering Questions

View More Questions