Step 1: Understanding the Question:
The question asks for the specific project management term that defines the amount of delay possible for an activity without impacting the very next activity in the sequence.
Step 2: Detailed Explanation:
Let's define the different types of float:
-
Total Float: This is the maximum amount of time an activity can be delayed without delaying the entire project's completion date.
-
Free Float: This is the amount of time an activity can be delayed without delaying the early start of any immediately following ("succeeding") activity.
This is a subset of Total Float.
It represents the "local" slack an activity has before it starts affecting its neighbours.
This perfectly matches the definition in the question.
-
Interfering Float: This is the difference between Total Float and Free Float.
It is the amount of slack that, if used, will not delay the project but will delay the start of a subsequent activity.
Step 3: Final Answer:
The time by which an activity can be delayed without affecting the start of a succeeding activity is called Free Float.
This corresponds to option (B).