The interfering float of activity R (in weeks, integer) is \(\underline{\hspace{2cm}}\).

Following five activities are associated with construction contract management. Choose the option showing the correct progressive sequence of the activities.

A construction project consists of five activities. The immediate successor activity relationship and duration of each activity are mentioned.

Find the total duration of the project in weeks.
A construction project consists of five activities. The immediate successor activity relationship and duration of each activity are mentioned.

Find the total duration of the project in weeks.
| Activity | Connecting Events | Three PERT Times (in Days) |
|---|---|---|
| P | 1 to 2 | 4 - 6 - 8 |
| Q | 1 to 3 | 5 - 6 - 13 |
| R | 2 to 5 | 6 - 8 - 22 |
| S | 2 to 3 | 8 - 11 - 14 |
| T | 3 to 5 | 2 - 4 - 12 |
| U | 3 to 4 | 4 - 8 - 18 |
| V | 4 to 5 | 5 - 7 - 15 |