Step 1: Calculate duration of each activity.
Formula:
\[
\text{Duration} = \frac{\text{Quantity}}{\text{Manpower} \times \text{Productivity}}
\]
- Activity A: \( \frac{96}{8 \times 3} = \frac{96}{24} = 4 \; \text{days} \)
- Activity B: \( \frac{252}{7 \times 4} = \frac{252}{28} = 9 \; \text{days} \)
- Activity C: \( \frac{275}{5 \times 5} = \frac{275}{25} = 11 \; \text{days} \)
- Activity D: \( \frac{126}{6 \times 3} = \frac{126}{18} = 7 \; \text{days} \)
Step 2: Dependencies.
- A → C
- B → C \& D
So:
- C can start only after both A and B are completed.
- D can start only after B is completed.
Step 3: Timeline.
- Start date = Jan 29.
- A: 4 days → finishes Feb 1.
- B: 9 days → finishes Feb 6.
- C: Starts after A and B = Feb 6, runs 11 days → finishes Feb 16.
- D: Starts after B = Feb 6, runs 7 days → finishes Feb 12.
Step 4: Project completion.
Since the project finishes when the last activity (C or D) finishes, completion = Feb 16.
Final Answer: \[ \boxed{\text{February 16}} \]
Following five activities are associated with construction contract management. Choose the option showing the correct progressive sequence of the activities.

A construction project consists of five activities. The immediate successor activity relationship and duration of each activity are mentioned.

Find the total duration of the project in weeks.
A construction project consists of five activities. The immediate successor activity relationship and duration of each activity are mentioned.

Find the total duration of the project in weeks.
The interfering float of activity R (in weeks, integer) is \(\underline{\hspace{2cm}}\).

