Production pattern for number of units (in cubic feet) per day 
For a truck that can carry 2,000 cubic ft, hiring cost per day is Rs. 1,000. Storing cost per cubic feet is Rs. 5 per day.
If the storage cost is reduced to Re 0.80 per cubic feet per day, then on which day(s), should the truck be hired?