Question:

In PERT technique, the time estimate of activities and probability of their occurrence follows:

Show Hint

Expected time ($t_e$) for the Beta distribution is calculated as: $t_e = \frac{t_o + 4t_m + t_p}{6}$. Note how the "Most Likely" time is weighted four times more than the extremes!
Updated On: May 20, 2026
  • Gumbel distribution
  • Beta distribution
  • Poisson distribution
  • Normal distribution
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Concept: The Program Evaluation and Review Technique (PERT) is a probabilistic method used when activity durations are uncertain. It uses three time estimates: Optimistic ($t_o$), Most Likely ($t_m$), and Pessimistic ($t_p$).

Step 1:
Activity Distribution vs. Project Distribution.
It is important to distinguish between the individual activity and the overall project:
Individual Activity: The time for a single activity in PERT is assumed to follow a $\beta$-distribution (Beta distribution). This is because the distribution is flexible and can be skewed to account for the fact that delays are more likely than finishing early.
Total Project Duration: According to the Central Limit Theorem, the total time for the critical path (sum of many activities) follows a Normal distribution.

Step 2:
Conclusion.
Since the question asks about the time estimate of "activities," the answer is the Beta distribution.