Question:

Amit can do a work in 12 days and Sagar in 15 days. If they work on it together for 4 days, then the fraction of the work that is left is:

Show Hint

Find the combined daily fraction of work, multiply by 4 days, then subtract from 1.
Updated On: Jul 15, 2026
  • 3/20
  • 3/5
  • 2/5
  • 2/20
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Set the total work.
Let total work \(=\text{LCM}(12,15)=60\) units.

Step 2: Find daily rates.
Amit's rate \(=\dfrac{60}{12}=5\) units/day. Sagar's rate \(=\dfrac{60}{15}=4\) units/day.

Step 3: Find work done in 4 days.
Combined rate \(=5+4=9\) units/day. Work done in 4 days \(=9\times4=36\) units.

Step 4: Find the work left.
Work left \(=60-36=24\) units. Fraction left \(=\dfrac{24}{60}=\dfrac{2}{5}\).

Step 5: Final Answer.
The fraction of work left is 2/5, so option C is correct.
Was this answer helpful?
0
0