Question:

A man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone?

Updated On: Apr 14, 2026
  • \(72\) days
  • \(64\) days
  • \(84\) days
  • \(24\) days
  • \(32\) days
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation


Concept: This is a
time and work problem:
  • Work rate = Work per day
  • Total work = sum of individual contributions

Step 1: Let total work = 1 unit.
\[ \text{Man + Boy rate} = \frac{1}{24} \]
Step 2: Work distribution.
  • First 20 days: both work
  • Last 6 days: only man works
\[ \text{Work in 20 days} = \frac{20}{24} = \frac{5}{6} \] Remaining work: \[ 1 - \frac{5}{6} = \frac{1}{6} \]
Step 3: Find man's rate.
\[ 6 \times \text{Man's rate} = \frac{1}{6} \Rightarrow \text{Man's rate} = \frac{1}{36} \]
Step 4: Find boy's rate.
\[ \text{Boy's rate} = \frac{1}{24} - \frac{1}{36} \] \[ = \frac{3 - 2}{72} = \frac{1}{72} \]
Step 5: Time taken by boy alone.
\[ \text{Time} = 72 \text{ days} \]
Step 6: Option analysis.
  • (A) 72: Correct \checkmark
  • (B) 64: Incorrect $\times$
  • (C) 84: Incorrect $\times$
  • (D) 24: Combined time $\times$
  • (E) 32: Incorrect $\times$

Conclusion:
Thus, the correct answer is
Option (A).
Was this answer helpful?
0
0

Top MAH MBA CET work Efficiency Questions

View More Questions