A and B can do a work in 8 days; B and C in 12 days; A, B and C together in 6 days. In how many days will A and C together do it?

Show Hint

To find the combined rate of two individuals, subtract the known pair rates from the triple rate to isolate individual speeds, then add them back together.
Updated On: Mar 27, 2026
  • 9
  • 6
  • 8
  • 10
  • 12
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation


Step 1: Analyse options.

- Work rate of $(A+B+C) = 1/6$. - Work rate of $(A+B) = 1/8$. - Work rate of $C = (A+B+C) - (A+B) = 1/6 - 1/8 = 1/24$. - Work rate of $(B+C) = 1/12$. - Work rate of $A = (A+B+C) - (B+C) = 1/6 - 1/12 = 1/12$. - Work rate of $(A+C) = 1/12 + 1/24 = 3/24 = 1/8$.
Step 2: Conclusion.

A and C together will complete the work in 8 days. Final Answer: (c) 8