Step 1: Define Variables:
Let the total work be $W$. Let the efficiencies (work per day) of Amal, Vimal, and Sunil be $a$, $v$, and $s$ respectively.
Step 2: Form Equations:
From the given information:
a + v &= \fracW150 (1)
v + s &= \fracW100 (2)
Also, from the second work pattern: $75a + 135v + 45s = W$.
Step 3: Solve for Individual Efficiencies:
We can treat $W$ as 1 (unit work) for convenience. Let $W = 1$ unit.
Then $a+v = \frac{1}{150}$ and $v+s = \frac{1}{100}$.
Substitute into $75a + 135v + 45s = 1$.
$75a + 90v + 45(v+s) = 1$
$75a + 90v + 45 \times \frac{1}{100} = 1$
$75a + 90v + 0.45 = 1$
$75a + 90v = 0.55 = \frac{55}{100} = \frac{11}{20}$.
Multiply the equation $a+v = \frac{1}{150}$ by 75: $75a + 75v = \frac{75}{150} = \frac{1}{2} = 0.5$.
Subtract this from $75a + 90v = 0.55$:
$(75a+90v) - (75a+75v) = 0.55 - 0.5 \implies 15v = 0.05 \implies v = \frac{0.05}{15} = \frac{1}{300}$.
Then $a = \frac{1}{150} - \frac{1}{300} = \frac{1}{300}$.
And $s = \frac{1}{100} - \frac{1}{300} = \frac{2}{300} = \frac{1}{150}$.
So, $a = \frac{1}{300}$, $v = \frac{1}{300}$, $s = \frac{1}{150}$.
Step 4: New Work Pattern:
Amal works on all days. Vimal works on every second day (days 2, 4, 6, ...). Sunil works on every third day (days 3, 6, 9, ...).
We need to find the number of days $N$ such that the total work done is at least 1.
Step 5: Calculate Work in a Cycle:
Consider a cycle of 6 days (LCM of 1, 2, 3).
Day 1: Amal only. Work = $a = \frac{1}{300}$.
Day 2: Amal + Vimal. Work = $a+v = \frac{1}{300}+\frac{1}{300} = \frac{2}{300}$.
Day 3: Amal + Sunil. Work = $a+s = \frac{1}{300}+\frac{1}{150} = \frac{1+2}{300} = \frac{3}{300}$.
Day 4: Amal + Vimal. Work = $\frac{2}{300}$.
Day 5: Amal only. Work = $\frac{1}{300}$.
Day 6: Amal + Vimal + Sunil. Work = $a+v+s = \frac{1}{300}+\frac{1}{300}+\frac{1}{150} = \frac{1+1+2}{300} = \frac{4}{300}$.
Total work in 6 days = $\frac{1+2+3+2+1+4}{300} = \frac{13}{300}$.
Step 6: Determine Number of Days:
Number of complete cycles = $\left\lfloor \frac{1}{\frac{13}{300}} \right\rfloor = \left\lfloor \frac{300}{13} \right\rfloor = 23$ cycles.
Work done in 23 cycles ($23 \times 6 = 138$ days) = $23 \times \frac{13}{300} = \frac{299}{300}$.
Remaining work = $1 - \frac{299}{300} = \frac{1}{300}$.
Day 139 is the first day of the next cycle. On day 139, Amal works (as it's day 1 of new cycl(e). Work done on day 139 = $\frac{1}{300}$, which exactly completes the work.
Total days required = $138 + 1 = 139$.