TS PGECET
List of top Questions asked in TS PGECET
If \(P\) is an orthogonal matrix of order \(3\times3\), \(A=\begin{bmatrix}1& 2& 2\\2& 1& 2\\2& 2& 1\end{bmatrix}\) and the eigenvalues of \(P^{T}AP\) are \(\alpha,\beta,\gamma\), then \(\alpha^2+\beta^2+\gamma^2=\)
TS PGECET - 2026
TS PGECET
Mathematics
Linear Algebra
Which of the following is a primary advantage of Monte Carlo simulation?
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
In a PERT network, the time estimate of an activity is as per the following: Optimistic time is \(4\) days, most likely time is \(6\) days and pessimistic time is \(14\) days. The expected time and standard deviation of the activity (in days) are respectively
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
In network analysis using the Critical Path Method (CPM), the critical path is the one with
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
In decision theory, which criterion assumes the decision-maker is pessimistic?
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
The primary objective of a balanced transportation problem is to
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
If two projects have the same PVB but Project A has a higher IRR than Project B, what is the usual recommendation when capital is limited?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Economics
Which of the following is a common form of mineral taxation applied in many countries to capture economic rent from mining operations?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Economics
The assignment problem is a special case of the transportation problem where
TS PGECET - 2026
TS PGECET
Mining Engineering
Systems Engineering
According to the UNFC (United Nations Framework Classification) system, which category represents the highest level of geological confidence and economic viability for a mineral deposit?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
A key component of a feasibility report that summarizes project risks, sensitivities, and contingency plans is called
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
The average grade of the mineral of a vein type of orebody with grade and thickness varying from place to place within the same orebody is arrived by
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
Which reserve estimation technique assumes a completely random distribution and is generally used only for initial rough estimates?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
Which financial metric indicates the time required for cumulative cash inflows to recover the initial investment in a mining project?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Economics
Which of the following profitability measures is most commonly used to compare mining projects of different sizes and lives?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Economics
Lerchs--Grossmann algorithm or nested pit shells are most commonly used for which stage of mine planning?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
Which of the following quality control practices is essential to detect and correct systematic errors in assay results during mineral resource estimation?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
In work-study (time and motion study) applied to mining operations, what is the primary purpose of a “rating factor”?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
Which sampling method is most commonly used for grade control in open-pit mining during production?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
Which of the following is NOT typically a major component of long-term mine planning?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
In reserve estimation, what does the term “kriging” primarily refer to in geostatistics?
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine planning and its components
For a mixture of inflammable gases, both the lower and upper explosibility limits can be computed using
TS PGECET - 2026
TS PGECET
Mining Engineering
Underground Hazards
The water gauge developed and quantity circulated with an axial flow fan depends on
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Ventilation
What does a Safety Management Plan (SMP) in mining primarily focus on?
TS PGECET - 2026
TS PGECET
Mining Engineering
Underground Hazards
The quantity of air taken by an auxiliary fan should not exceed
TS PGECET - 2026
TS PGECET
Mining Engineering
Mine Ventilation
Prev
1
...
37
38
39
40
41
...
243
Next