Concept:
This is a work-done problem. The combined work rate of multiple workers is the sum of their individual rates.
Step 1: Determine the work rate of A and B.
A completes the work in 16 days.
\[
\text{Rate of A} = \frac{1}{16} \text{ work/day}
\]
A takes 8 days less than B, meaning B takes \( 16 + 8 = 24 \) days.
\[
\text{Rate of B} = \frac{1}{24} \text{ work/day}
\]
Step 2: Determine the combined rate of A, B, and C.
Given they complete it in 8 days together:
\[
\text{Rate (A+B+C)} = \frac{1}{8} \text{ work/day}
\]
Step 3: Calculate the rate of C.
\[
\text{Rate of C} = \text{Rate (A+B+C)} - (\text{Rate of A} + \text{Rate of B})
\]
\[
\text{Rate of C} = \frac{1}{8} - \left( \frac{1}{16} + \frac{1}{24} \right)
\]
\[
\text{Rate of C} = \frac{1}{8} - \frac{5}{48} = \frac{6 - 5}{48} = \frac{1}{48}
\]
Step 4: Calculate the days taken by C.
Since the rate of C is \( \frac{1}{48} \), C takes 48 days to complete the work alone.
\centerline{{48}}