Question:

Three workers A, B, and C are working on a piece of work. A and B can complete the work in 18 days, B and C in 24 days, and C and A in 36 days. If A alone works on the job, how many days will it take for A to complete the job?

Show Hint

When efficiencies of pairs of workers are given, first add all pair equations. This gives the combined efficiency of all workers and helps determine individual efficiencies easily.
Updated On: Jun 12, 2026
  • \(40\)
  • \(45\)
  • \(48\)
  • \(50\)
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Concept: If the work rates of A, B and C are represented by \(a\), \(b\), and \(c\) respectively, then: \[ a+b=\frac1{18}, \qquad b+c=\frac1{24}, \qquad c+a=\frac1{36} \] Adding all three equations allows us to determine the combined rate of all three workers.

Step 1:
Add the three given equations. \[ (a+b)+(b+c)+(c+a) = \frac1{18}+\frac1{24}+\frac1{36} \] Taking LCM \(=72\), \[ 2(a+b+c) = \frac4{72}+\frac3{72}+\frac2{72} = \frac9{72} = \frac18 \] Therefore, \[ a+b+c=\frac1{16} \]

Step 2:
Find A's individual work rate. \[ a=(a+b+c)-(b+c) \] \[ a=\frac1{16}-\frac1{24} \] Taking LCM \(48\), \[ a=\frac3{48}-\frac2{48} = \frac1{48} \]

Step 3:
Find the number of days required by A alone. Since A completes \[ \frac1{48} \] of the work per day, A alone requires \[ 48 \] days to complete the entire work. \[ \boxed{48} \]
Was this answer helpful?
0
0