Concept:
If the work rates of A, B and C are represented by \(a\), \(b\), and \(c\) respectively, then:
\[
a+b=\frac1{18}, \qquad b+c=\frac1{24}, \qquad c+a=\frac1{36}
\]
Adding all three equations allows us to determine the combined rate of all three workers.
Step 1: Add the three given equations.
\[
(a+b)+(b+c)+(c+a)
=
\frac1{18}+\frac1{24}+\frac1{36}
\]
Taking LCM \(=72\),
\[
2(a+b+c)
=
\frac4{72}+\frac3{72}+\frac2{72}
=
\frac9{72}
=
\frac18
\]
Therefore,
\[
a+b+c=\frac1{16}
\]
Step 2: Find A's individual work rate.
\[
a=(a+b+c)-(b+c)
\]
\[
a=\frac1{16}-\frac1{24}
\]
Taking LCM \(48\),
\[
a=\frac3{48}-\frac2{48}
=
\frac1{48}
\]
Step 3: Find the number of days required by A alone.
Since A completes
\[
\frac1{48}
\]
of the work per day, A alone requires
\[
48
\]
days to complete the entire work.
\[
\boxed{48}
\]