The chart below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).
The Capacity Factor of a power generation technology is defined as: \[ \text{Capacity Factor} = \frac{\text{Electricity Generation (MWh)}}{\text{Installed Capacity (MW)} \times 1000 \, \text{(h)}} \] Which one of the given technologies has the highest Capacity Factor?
Step 1: Analyze the given data. From the chart: Installed Capacity of T1 = 20 MW, Electricity Generation of T1 = 12000 MWh. Installed Capacity of T2 = 30 MW, Electricity Generation of T2 = 9000 MWh. Installed Capacity of T3 = 40 MW, Electricity Generation of T3 = 8000 MWh. Installed Capacity of T4 = 50 MW, Electricity Generation of T4 = 7000 MWh.
Step 2: Calculate Capacity Factor for each technology. Using the formula: \[ \text{Capacity Factor} = \frac{\text{Electricity Generation (MWh)}}{\text{Installed Capacity (MW)} \times 1000} \] For T1: \[ \text{Capacity Factor} = \frac{12000}{20 \times 1000} = 0.6 \, (60\%). \] For T2: \[ \text{Capacity Factor} = \frac{9000}{30 \times 1000} = 0.3 \, (30\%). \] For T3: \[ \text{Capacity Factor} = \frac{8000}{40 \times 1000} = 0.2 \, (20\%). \] For T4: \[ \text{Capacity Factor} = \frac{7000}{50 \times 1000} = 0.14 \, (14\%). \]
Step 3: Compare the Capacity Factors. The Capacity Factors are: \[ \text{T1: } 60\%, \quad \text{T2: } 30\%, \quad \text{T3: } 20\%, \quad \text{T4: } 14\%. \] The highest Capacity Factor is for T1, with \( 60\% \).
Conclusion: The technology with the highest Capacity Factor is T1.
Consider a five-digit number PQRST that has distinct digits P, Q, R, S, and T, and satisfies the following conditions:
1. \( P<Q \)
2. \( S>P>T \)
3. \( R<T \)
If integers 1 through 5 are used to construct such a number, the value of P is:
In the context of the given figure, which one of the following options correctly represents the entries in the blocks labelled (i), (ii), (iii), and (iv), respectively?

Consider a five-digit number PQRST that has distinct digits P, Q, R, S, and T, and satisfies the following conditions:
1. \( P<Q \)
2. \( S>P>T \)
3. \( R<T \)
If integers 1 through 5 are used to construct such a number, the value of P is:
In the context of the given figure, which one of the following options correctly represents the entries in the blocks labelled (i), (ii), (iii), and (iv), respectively?

A bag contains Violet (V), Yellow (Y), Red (R), and Green (G) balls. On counting them, the following results are obtained:
(i) The sum of Yellow balls and twice the number of Violet balls is 50.
(ii) The sum of Violet and Green balls is 50.
(iii) The sum of Yellow and Red balls is 50.
(iv) The sum of Violet and twice the number of Red balls is 50.
For the clock shown in the figure, if
O* = O Q S Z P R T, and
X* = X Z P W Y O Q,
then which one among the given options is most appropriate for P*?
