Step 1: Size of the job:
Raja works every day. From Feb 25 to Apr 2, 1996 (leap year) the days are: Feb 25 to 29 gives 5 days, March gives 31 days and April 1 and April 2 give 2 days, so the total is 38 days. The job is 38 person-days.
Step 2: Daily output of T and S together (starting Sunday):
Sunday: S off, T works = 1. Monday: 2. Tuesday: T off, S works = 1. Wednesday: 2. Thursday: T off = 1. Friday: 2. Saturday: S off = 1.
One full week gives \( 1 + 2 + 1 + 2 + 1 + 2 + 1 = 10 \) person-days.
Step 3: Find the finishing day:
3 weeks give 30 person-days. These 21 days run from Sunday, Feb 25 to Saturday, Mar 16. The next day, Sunday, Mar 17, starts with 30 done and 8 left.
Sunday Mar 17: 1 (total 31). Monday Mar 18: 2 (33). Tuesday Mar 19: 1 (34). Wednesday Mar 20: 2 (36). Thursday Mar 21: 1 (37). Friday Mar 22: 2 (39), which completes the job (only 1 unit is actually needed).
Step 4: Conclude:
T and S complete the job on Friday, March 22, 1996.
Final Answer:
The correct option is (2): March 22, 1996