Question:

The Weirdo Holiday Resort follows a particular system of holidays for its employees. People are given holidays on the days where the first letter of the day of the week is the same as the first letter of their names. All employees work at the same rate.
Starting on February 25, 1996 (Sunday), if Raja had finished his job on April 2, 1996, when would T and S together likely to have completed the job, had they started on the same day as Raja?

Show Hint

Raja never has a holiday, so the job equals the number of days from Feb 25 to Apr 2 inclusive. Then track T and S day by day: T is off on Tuesday and Thursday, S is off on Saturday and Sunday.
Updated On: Nov 4, 2026
  • March 15, 1996
  • March 22, 1996
  • March 14, 1996
  • Data insufficient
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Size of the job:
Raja works every day. From Feb 25 to Apr 2, 1996 (leap year) the days are: Feb 25 to 29 gives 5 days, March gives 31 days and April 1 and April 2 give 2 days, so the total is 38 days. The job is 38 person-days.

Step 2: Daily output of T and S together (starting Sunday):
Sunday: S off, T works = 1. Monday: 2. Tuesday: T off, S works = 1. Wednesday: 2. Thursday: T off = 1. Friday: 2. Saturday: S off = 1.
One full week gives \( 1 + 2 + 1 + 2 + 1 + 2 + 1 = 10 \) person-days.

Step 3: Find the finishing day:
3 weeks give 30 person-days. These 21 days run from Sunday, Feb 25 to Saturday, Mar 16. The next day, Sunday, Mar 17, starts with 30 done and 8 left.
Sunday Mar 17: 1 (total 31). Monday Mar 18: 2 (33). Tuesday Mar 19: 1 (34). Wednesday Mar 20: 2 (36). Thursday Mar 21: 1 (37). Friday Mar 22: 2 (39), which completes the job (only 1 unit is actually needed).

Step 4: Conclude:
T and S complete the job on Friday, March 22, 1996.

Final Answer:
The correct option is (2): March 22, 1996