Step 1: Size of the job:
No day of the week begins with R, so Raja works every day. 1996 is a leap year, so from Sunday, February 25 to Saturday, March 2 he works on Feb 25, 26, 27, 28, 29, Mar 1 and Mar 2, which is 7 days. The job is therefore 7 person-days.
Step 2: Holidays of T and J:
T gets holidays on Tuesday and Thursday. No day starts with J, so J never gets a holiday.
Step 3: Count the work done each day (starting Sunday):
Sunday: T and J both work, so 2 (total 2).
Monday: 2 (total 4).
Tuesday: T is on holiday, only J works, so 1 (total 5).
Wednesday: 2 (total 7). The job of 7 person-days is complete.
Step 4: Conclude:
T and J finish on Wednesday, the 4th day (Sunday to Wednesday), so they take 4 days.
Final Answer:
The correct option is (3): 4 days