The Weirdo Holiday Resort follows a particular system of holidays for its employees. People are given holidays on the days where the first letter of the day of the week is the same as the first letter of their names. All employees work at the same rate.
Raja starts working on February 25 (Sunday), 1996, and finishes the job on March 2, 1996. How much time would T and J take to finish the same job if both start on the same day as Raja?

Show Hint

Raja's name starts with R, and no day starts with R, so he never gets a holiday. Count the job in "person-days", then see how fast T and J (who have holidays) work.
Updated On: Nov 4, 2026
  • Either a or b
  • 5 days
  • 4 days
  • Cannot be determined
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Size of the job:
No day of the week begins with R, so Raja works every day. 1996 is a leap year, so from Sunday, February 25 to Saturday, March 2 he works on Feb 25, 26, 27, 28, 29, Mar 1 and Mar 2, which is 7 days. The job is therefore 7 person-days.

Step 2: Holidays of T and J:
T gets holidays on Tuesday and Thursday. No day starts with J, so J never gets a holiday.

Step 3: Count the work done each day (starting Sunday):
Sunday: T and J both work, so 2 (total 2).
Monday: 2 (total 4).
Tuesday: T is on holiday, only J works, so 1 (total 5).
Wednesday: 2 (total 7). The job of 7 person-days is complete.

Step 4: Conclude:
T and J finish on Wednesday, the 4th day (Sunday to Wednesday), so they take 4 days.

Final Answer:
The correct option is (3): 4 days