Question:

In project appraisal, Net Present Value (NPV) is calculated by:

Show Hint

NPV > 0 = Accept project, NPV < 0 = Reject project.
  • Subtracting initial investment from total cash inflows
  • Dividing cash inflows by initial cost
  • Subtracting present value of outflows from present value of inflows
  • Adding future inflows without discounting
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Approach Solution - 1

NPV = PV of Cash Inflows – PV of Cash Outflows. It considers the time value of money — future cash flows are discounted back to present value using a discount rate. A positive NPV means the project is expected to generate profit above the cost of capital.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

Formula Recall: NPV has one standard formula worth memorizing directly: PV of Inflows − PV of Outflows.

This matches option 3 exactly — it accounts for the time value of money by discounting future cash flows back to today before subtracting.

Option 1 ignores discounting (uses raw totals), option 2 describes a ratio (more like a Benefit-Cost Ratio), and option 4 skips discounting entirely — none of these is the actual NPV formula.
Was this answer helpful?
0
0