Question:

Arun, Tarun and Varun work for 24, 21 and 15 days respectively and get paid 2160, 2400 and 2160 rupees respectively. They get paid the same even if they work for a partial day. If the work has to be completed within 10 days or less, what is the minimum amount that has to be paid to complete the entire task?

Show Hint

For each worker, compare pay divided by the number of days they would take alone; this ratio equals their total quoted payment and shows who is most cost-efficient. Then check whether skipping the costliest worker still lets the remaining workers finish within the deadline.
Updated On: Aug 17, 2026
Show Solution
collegedunia
Verified By Collegedunia

Correct Answer: 2160

Approach Solution - 1

Approach: When wages are flat per job, the smart lens is cost per unit of work. Find each worker's cost-per-unit, pick the cheapest, but make sure the chosen team can still finish within 10 days.

Step 1: Take total work \(= \text{LCM}(24, 21, 15) = 840\) units. Daily output:
Arun \(= 840/24 = 35\), Tarun \(= 840/21 = 40\), Varun \(= 840/15 = 56\) units/day.

Step 2: Each man's total wage is fixed for the whole job, so his cost per unit is (total pay)/840:
Arun \(= 2160/840 = 18/7\), Tarun \(= 2400/840 = 20/7\), Varun \(= 2160/840 = 18/7\) rs/unit.

Step 3: Arun and Varun are the cheap pair at \(18/7\) per unit; Tarun is dearer. So build the team from Arun and Varun only and pay Tarun nothing.

Step 4: Can Arun + Varun finish in 10 days? Combined rate \(= 35 + 56 = 91\) units/day, so time \(= 840/91 \approx 9.23\) days \(\le 10\). The deadline is met.

Step 5: Since every one of the 840 units is done at \(18/7\) rs, cost \[ = 840 \times \frac{18}{7} = 120 \times 18 = 2160. \]

Final Answer: Minimum amount \(= \boxed{2160}\) rupees.
Was this answer helpful?
2
2
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

Approach: Since each person is paid a flat daily wage but produces a fixed daily share of work, work out the cost per unit of total work for each, not the daily wage, and see who is cheapest.

Daily wage: Arun \(2160/24=90\), Tarun \(2400/21\approx114.3\), Varun \(2160/15=144\). Daily work rate (as a fraction of the whole job): Arun \(\tfrac1{24}\), Tarun \(\tfrac1{21}\), Varun \(\tfrac1{15}\).

Cost per unit of the whole job \(=\dfrac{\text{daily wage}}{\text{daily work rate}}\), which simplifies back to each person's total quoted payment: Arun \(2160\), Tarun \(2400\), Varun \(2160\) \(-\) meaning finishing the ENTIRE job using only Arun, only Varun, or any split between the two always costs exactly Rs. \(2160\), while any contribution from Tarun costs more per unit of work.

So the cheapest plan uses only Arun and Varun together. Their combined daily rate is \(\tfrac{1}{24}+\tfrac{1}{15}=\tfrac{13}{120}\), so together they finish in \(\tfrac{120}{13}\approx9.23\) days, within the \(10\)-day limit, at the minimum possible cost of \[ \boxed{\text{Rs. }2160} \]
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -3

Concept:
  • Think in terms of two separate quantities for each person: a daily wage (pay divided by the number of days they need to finish the job alone) and a daily work rate (the fraction of the job completed in one day).
  • For any set of workers working together for $T$ days, total cost equals $T$ times the sum of their daily wages, and the job finishes when $T$ times the sum of their daily rates equals $1$.
  • Combining these two facts, the cost of using a particular set of workers to finish the whole job equals (sum of daily wages) divided by (sum of daily rates); comparing this ratio for different sets shows which combination is cheapest.

Step 1: Find daily wage and daily rate for each person.
Arun: wage $=2160/24=90$ rupees/day, rate $=1/24$ of the job per day.
Tarun: wage $=2400/21=800/7$ rupees/day, rate $=1/21$ of the job per day.
Varun: wage $=2160/15=144$ rupees/day, rate $=1/15$ of the job per day.

Step 2: Notice a shortcut: wage divided by rate always gives back the total pay.
For one person, (daily wage)/(daily rate) equals (pay/days)/(1/days), which is just pay. So Arun and Varun both give $2160$, while Tarun gives $2400$. This ratio measures how expensive it is to get one full job done by that person alone, and Tarun is the costliest.

Step 3: Exclude the costliest worker and check the deadline.
Since Tarun costs more per unit of work, use only Arun and Varun. Their combined rate is $\dfrac{1}{24}+\dfrac{1}{15}=\dfrac{5+8}{120}=\dfrac{13}{120}$ of the job per day, so together they finish in $\dfrac{120}{13}\approx9.23$ days, which is within the $10$-day limit.

Step 4: Compute the total cost for this pair.
Total cost $=\dfrac{\text{sum of daily wages}}{\text{sum of daily rates}}=\dfrac{90+144}{13/120}=\dfrac{234\times120}{13}=18\times120=2160$.

Final Answer: The minimum amount to be paid is $2160$ rupees.
Was this answer helpful?
0
0

Top CAT Quantitative Aptitude Questions

View More Questions

Top CAT Time and Work Questions

View More Questions