Question:

Arrange the phases in the project cycle in the correct order:
A. Evaluation
B. Monitoring
C. Appraisal
D. Formulation
E. Identification

Show Hint

Exam Tip: A useful mnemonic to remember the project cycle is I F A I M E:
Identification, Formulation, Appraisal, Implementation, Monitoring, Evaluation.
  • E, D, C, B, A
  • D, E, C, B, A
  • A, D, E, C, B
  • A, E, D, C, B
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Understanding the Concept:
This question tests knowledge of the project management cycle. The project cycle is a sequence of stages that a project goes through from its conception to its completion.

Step 2: The Phases of a Project Cycle:

The typical phases in a project cycle are:
Identification: Identifying potential projects that align with the organization's goals.
Formulation: Developing the project idea into a detailed plan, including objectives, activities, budget, and timeline.
Appraisal: Evaluating the project plan to assess its feasibility, viability, and potential impact.
Implementation: Executing the project plan.
Monitoring: Continuously tracking the project's progress, performance, and resources to ensure it stays on track.
Evaluation: Assessing the project's outcomes and impact after completion to determine if the objectives were met. The sequence is: Identification \(\rightarrow\) Formulation \(\rightarrow\) Appraisal \(\rightarrow\) Monitoring \(\rightarrow\) Evaluation.

Step 3: Arranging the Given Terms:

Given the terms: A. Evaluation, B. Monitoring, C. Appraisal, D. Formulation, E. Identification.
The correct order is:
• E. Identification
• D. Formulation
• C. Appraisal
• B. Monitoring
• A. Evaluation

Step 4: Final Answer:

The correct sequence is E, D, C, B, A, which corresponds to option (A).