Step 1: Understanding the Concept:
To minimize the completion time of an order, tasks must be allocated to the two available employees (Anish and Bani) such that they work in parallel where possible.
We also utilize the automatic fryer's ability to run independently once started.
Detailed Explanation:
Let us analyze Client 1's order placed at 10:00:
- Items ordered: 1 burger, 3 portions of fries, 1 order of ice cream.
- Task durations:
1. Burger: 10 minutes (requires 1 employee).
2. Ice cream: 2 minutes (requires 1 employee).
3. Fries: 5 minutes in the automatic fryer (requires an employee only to start/stop the fryer, which takes negligible time).
Let us allocate the tasks at 10:00:
- Anish starts preparing the burger at 10:00. This task is completed at 10:10.
- Simultaneously, Bani starts the automatic fryer with 3 portions of fries at 10:00. These fries are ready at 10:05.
- Since the fryer operates automatically and does not require constant attention, Bani is free to immediately start preparing the ice cream at 10:00. The ice cream is ready at 10:02.
Now let us track the completion times of all components of Client 1's order:
- Ice cream is ready at 10:02.
- Fries are ready at 10:05.
- Burger is ready at 10:10.
An order is considered completely served only when all of its components are ready.
The last item (the burger) is completed at 10:10. Thus, the order is completely served at 10:10.
Step 2: Final Answer:
The order is completely served at 10:10, which corresponds to Option (B).