Step 1: Understanding the Concept:
A job is made of two elements, A and B, each timed three times using a stopwatch.
We must convert these raw observed times into a standard time per job, and then convert that standard time into an hourly production rate.
Step 2: Key Formula or Approach:
Average Observed Time = sum of readings divided by number of readings.
Normal Time = Average Observed Time \( \times \) Rating Factor.
Standard Time (per element) = Normal Time \( \times (1 + \text{Allowance Fraction}) \), and since allowance is a common percentage add-on, we can apply it to each element individually and then add the two standard times together to get the standard time for the whole job.
Step 3: Detailed Explanation:
Element A:
\[ \text{Average OT}_A = \frac{20 + 25 + 21}{3} = \frac{66}{3} = 22 \text{ s} \]
\[ NT_A = 22 \times 1.05 = 23.1 \text{ s} \]
\[ ST_A = 23.1 \times 1.20 = 27.72 \text{ s} \]
Element B:
\[ \text{Average OT}_B = \frac{19 + 17 + 18}{3} = \frac{54}{3} = 18 \text{ s} \]
\[ NT_B = 18 \times 0.90 = 16.2 \text{ s} \]
\[ ST_B = 16.2 \times 1.20 = 19.44 \text{ s} \]
Adding the standard times of the two elements gives the standard time for one complete job:
\[ ST = 27.72 + 19.44 = 47.16 \text{ s/unit} \]
Now convert this to an hourly rate using the 3600 seconds available in one hour:
\[ \text{Output per hour} = \frac{3600}{47.16} = 76.34 \text{ units} \]
Final Answer:
Since the worker cannot complete a fractional unit within the hour, the standard output rounds down to the nearest whole unit.
\[ \boxed{76 \text{ units per hour}} \]