Question:

A time phased stock replenishment plan for all levels of supply chain is called

Show Hint

DRP extends MRP logic to distribution networks.
Updated On: Jul 4, 2026
  • DRP
  • ERP
  • MRPII
  • MRP
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Concept: Supply chain planning systems use time-phased scheduling to ensure materials and products are available at the right time in the right quantity across multiple distribution levels.

Step 1:
Understand DRP.
Distribution Requirements Planning (DRP) is:
• A time-phased inventory planning system
• Used for distribution networks
• Extends MRP logic to supply chain levels

Step 2:
Compare systems.

• MRP → production materials planning
• MRPII → integrated manufacturing planning
• ERP → enterprise-wide system
• DRP → distribution stock replenishment (correct)

Step 3:
Final conclusion.
\[ \boxed{\text{Distribution Requirements Planning (DRP)}} \] Thus, \[ \boxed{\text{Option (A) is correct.}} \]