Concept:
Work-time problems involve calculating rates: $Rate = 1 / Time$.
Step 1: Calculate rates.
- Pipe P rate = $1/2$ tank per hour.
- Pipe Q rate = $1/6$ tank per hour.
Step 2: Calculate fill status at 11 am.
Pipe P works alone from 10 am to 11 am (1 hour).
Tank filled = $1/2$. Remaining = $1/2$.
Step 3: Calculate time for both pipes.
Combined rate = $1/2 + 1/6 = 3/6 + 1/6 = 4/6 = 2/3$.
Time = $Remaining / Rate = (1/2) / (2/3) = 3/4$ hours.
$3/4 \text{ hours} = 45 \text{ minutes}$.
equation
11 am + 45 minutes = 11:45 AM
equation
center
11:45 AM
center