We will calculate the design spacing of stirrups using the formula for shear reinforcement in an RCC beam.
Step 1: Calculate the shear capacity of concrete \(V_c\) The shear capacity provided by the concrete \(V_c\) is calculated using the formula: \[ V_c = \tau_c \times b \times d \] where:
\( \tau_c \) = 0.35 N/mm² (design shear strength of concrete),
\( b \) = 250 mm (width of the beam),
\( d \) = 400 mm (effective depth of the beam).
Substituting the values: \[ V_c = 0.35 \times 250 \times 400 = 35,000 \, {N} = 35 \, {kN} \] Step 2: Calculate the shear force to be resisted by stirrups \(V_s\) The total shear force \(V_u\) is given as 120 kN. The portion of this shear force to be resisted by the stirrups is the remaining portion after the concrete’s contribution. Therefore, \[ V_s = V_u - V_c = 120 \, {kN} - 35 \, {kN} = 85 \, {kN} \] Step 3: Calculate the area of shear reinforcement per leg \(A_v\) The stirrups are two-legged, and each leg has a diameter of 8 mm. The area of one stirrup leg \(A_v\) is given by: \[ A_v = 2 \times \frac{\pi}{4} \times (8)^2 = 2 \times \frac{\pi}{4} \times 64 = 2 \times 50.24 = 100.48 \, {mm}^2 \] Step 4: Use the formula for shear reinforcement capacity The formula for shear reinforcement capacity is: \[ V_s = \frac{A_v \times f_y}{s} \] where:
\( A_v \) = area of one stirrup leg (100.48 mm²),
\( f_y \) = 415 N/mm² (yield stress of steel),
\( s \) = spacing between stirrups (the unknown we need to solve for),
\( V_s \) = shear force resisted by the stirrups (85 kN).
Rearranging the formula to solve for \(s\): \[ s = \frac{A_v \times f_y}{V_s} \] Substituting the known values: \[ s = \frac{100.48 \times 415}{85,000} = \frac{41,795.2}{85,000} \approx 0.49 \, {m} = 160 \, {mm} \] Conclusion: The design spacing (c/c) of the stirrups is 160 mm (rounded to the nearest integer).
Match the heritage conservation charters in Group I with their focus areas in Group II.

Match the names of the gardens in Group I with their type in Group II. 
Match the Place(s)/Event(s) in Group I with the corresponding Heritage Significance/Characteristics in Group II.

Match the Urban Design Concepts in Group I with their corresponding Proponents in Group II.

Match the following items of work in Group-I with their corresponding units of measurement in Group-II.

Match the following principles of design in Group-I to their corresponding descriptions in Group-II.

A construction project consists of four activities. The duration, relationship, and cost parameters are given in the table. The indirect cost of the project is INR 5000 per week. If the project has to be completed by 12 weeks, the total project cost will be, INR _________ (Answer in integer)