| Defect in deep drawing cup | Reason | ||
|---|---|---|---|
| P | Orange peel on the surface of cup | 1 | No blank holding force |
| Q | Wrinkling at the flange of cup | 2 | Very small corner radius of the punch |
| R | Tearing at the bottom corner of cup | 3 | Large grain size in the blank material |
| S | Earring at the top edge of the cup | 4 | Anisotropy of the blank material |

A machine shop has received four jobs A, B, C, and D for processing on a single CNC machine. All jobs are available for processing on the first day of the production schedule calendar, and processing times and due dates as applicable on the first day are given below. Using earliest due date rule, the average tardiness (in days) is _________. 