Question:

A key component of a feasibility report that summarizes project risks, sensitivities, and contingency plans is called

Show Hint

A feasibility report always includes \[ \boxed{ \text{Risk Assessment} + \text{Sensitivity Analysis} } \] to evaluate project uncertainty.
Updated On: Jul 14, 2026
  • Mineral Resource Statement
  • Risk Assessment and Sensitivity Analysis
  • Capital Cost Estimate
  • Mining Method Selection
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Recall the contents of a feasibility report. A feasibility report evaluates the technical, economic, environmental, and operational viability of a mining project.

Step 2:
Identify the section dealing with uncertainties. The section that evaluates project risks, performs sensitivity studies, and discusses contingency measures is \[ \boxed{\text{Risk Assessment and Sensitivity Analysis}.} \] Hence, \[ \boxed{(B)} \] is the correct answer.