Approach: Stop thinking in fractions. Assume the total work is the LCM of 12 and 18, so both rates become clean whole numbers \(-\) that is the fastest way to handle any "start together, one leaves" problem.
Step 1: Let the total work \(= \text{LCM}(12, 18) = 36\) units.
Step 2: Find the daily rates.
A does \(\frac{36}{12} = 3\) units/day, B does \(\frac{36}{18} = 2\) units/day.
Step 3: For the first 4 days both work together at \(3 + 2 = 5\) units/day.
\[ \text{Work done in 4 days} = 5 \times 4 = 20 \text{ units} \]
Step 4: A now leaves. Remaining work \(= 36 - 20 = 16\) units, and only B continues at 2 units/day.
\[ \text{Days for B} = \frac{16}{2} = 8 \text{ days} \]
Final Answer: B takes 8 more days.