Question:

160 people are employed to finish the work in 120 days. After 40 days it was found that only \(\frac{1}{5}\) of the work is completed. To complete the work in the scheduled time, how many more people are to be employed?

Show Hint

Always identify the remaining work and remaining time correctly before setting up the equation for the second phase of the project.
Updated On: Jun 15, 2026
  • 40
  • 80
  • 120
  • 160
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Concept: This problem uses the work-days relationship formula: \(\frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2}\), where \( M \) is the number of workers, \( D \) is the number of days, and \( W \) is the fraction of work completed.

Step 1:
Analyze the initial work phase.
Given: \( M_1 = 160 \), \( D_1 = 40 \), \( W_1 = \frac{1}{5} \).

Step 2:
Determine the requirements for the remaining work.
Remaining work (\( W_2 \)) = \( 1 - \frac{1}{5} = \frac{4}{5} \). Remaining time (\( D_2 \)) = \( 120 - 40 = 80 \) days.

Step 3:
Apply the formula to find the total workers needed (\( M_2 \)).
\[ \frac{160 \times 40}{1/5} = \frac{M_2 \times 80}{4/5} \] \[ 160 \times 40 \times 5 = M_2 \times 80 \times \frac{5}{4} \] \[ 32000 = M_2 \times 100 \implies M_2 = 320 \]

Step 4:
Calculate additional workers.
\[ \text{Additional workers} = M_2 - M_1 = 320 - 160 = 160 \] \centerline{{160}}
Was this answer helpful?
0
0