The table below shows the raw material requirement (in units) for a crank-shaft machining line of a major automobile manufacturer based in western India. Company policy requires that raw material be kept in stock at least one day in advance, so an order placed on a given day is delivered and ready for use only from the next day onward, unless a delay is stated.
| Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
| Units | 50 | 25 | 30 | 20 | 5 | 6 | 2 | 10 | 15 | 20 | 25 | 10 | 5 | 20 | 10 |
If the raw material inventory on Day 0 was 165 units, the manager needs to place an order latest by which day?
If the raw material inventory on Day 0 was 73 units and the manager orders 17, 53 and 86 units on the first, second and fourth day respectively, when does he need to order next?
If the raw material supplier starts acting unreliable and delays deliveries by 48 hours, which day's production will be hit if the starting inventory on Day 0 is 163 units and an order is placed on the morning of Day 7?
Suppose the raw material inventory on Day 0 was 73 units and the manager orders 17, 53 and 86 units on the first, second and fourth day respectively, so that the next order falls due on Day 13. If the cost of placing an order is Rs. 650 per order, find the minimum cost incurred over the whole 15 day cycle.
If the daily pilferage is 5 units, find the minimum number of units that need to be ordered through the whole cycle, given that the inventory on Day 0 is 100 units and the inventory ends at zero after Day 15.