Question:

The Slack time in PERT analysis

Show Hint

Critical events and activities always have zero slack (or float). Non-critical events have positive slack.
Updated On: Jul 23, 2026
  • Can never be greater than zero
  • Is always zero for critical activities
  • Can never be less than zero
  • Is minimum for critical events
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Concept: Slack is the amount of time by which an event may be delayed without affecting the project completion time. It is calculated as \[ \boxed{\text{Slack} = \text{Latest Event Time} - \text{Earliest Event Time}.} \] For critical events, \[ \text{Latest Event Time}=\text{Earliest Event Time}, \] therefore the slack is zero, which is the minimum possible value.

Step 1:
Define slack. Slack represents the scheduling flexibility available for an event. \[ \text{Slack}=L-E. \]

Step 2:
Identify the critical event. For every critical event, \[ L=E, \] hence \[ \boxed{\text{Slack}=0.} \] Since zero is the minimum value of slack, \[ \boxed{\text{Slack is minimum for critical events}.} \] Therefore, the correct option is \[ \boxed{(D)\;\text{Is minimum for critical events}.} \]