Question:

The Singareni Collieries Company Limited (SCCL) has set up a 20 kW pilot geothermal power plant in Telangana at

Show Hint

Geothermal energy uses the natural heat of the Earth to generate electricity. The Singareni Collieries Company Limited (SCCL) set up a small pilot geothermal power plant in Telangana to test this technology.
Updated On: Jun 16, 2026
  • Ramagundam
  • Satthupally
  • Bellampally
  • Manuguru
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Concept:
Geothermal energy uses the natural heat of the Earth to generate electricity. The Singareni Collieries Company Limited (SCCL) set up a small pilot geothermal power plant in Telangana to test this technology.

Step 1:
SCCL is a coal-mining company operating in the Godavari valley coalfields of Telangana, and Manuguru is one of its major mining areas.

Step 2:
The 20 kW pilot geothermal power plant was established at Manuguru in the Bhadradri Kothagudem district, making it the location of this demonstration project.

Answer: Option (4) — Manuguru.