The project activities are given in the following table along with the duration and dependency. \[ \begin{array}{|c|c|c|} \hline \text{Activities} & \text{Duration (days)} & \text{Depends on} \\ \hline P & 10 & - \\ Q & 12 & - \\ R & 5 & P \\ S & 10 & Q \\ T & 10 & P, Q \\ \hline \end{array} \] Which one of the following combinations is correct?