Question:
The optimistic, most likely duration and the pessimistic time estimate in a network are 5, 6 and 10 months respectively. The expected time is -
CUET (PG) - 2023
CUET (PG)
Updated On:
Mar 21, 2024
6 months
6.5 months
7 months
7.5 months
Show Solution
Verified By Collegedunia
The Correct Option is
B
Solution and Explanation
The correct answer is (B) : 6.5 months.
Download Solution in PDF
Was this answer helpful?
0
0
Top CUET PG Construction and Management Questions
The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
CUET (PG) - 2023
Construction and Management
Estimation and Specification
View Solution
For the construction of retaining structures, the type of concrete mix to be used is
CUET (PG) - 2023
Construction and Management
Form and Structure
View Solution
Top CUET PG Estimation and Specification Questions
The optimistic, most likely duration and the pessimistic time estimate in a network are 6, 10 and 12 months respectively. The expected time is -
CUET (PG) - 2023
Construction and Management
Estimation and Specification
View Solution
Top CUET PG Questions
Spot the error in the sentence: "Neither of the two brothers are ready to go."
CUET (PG) - 2026
Vocabulary
View Solution
Which of the following is the antonym of the word "Fragile"?
CUET (PG) - 2026
Vocabulary
View Solution
What is the dilution factor of blood and RBC diluting fluid for a total erythrocyte count?
CUET (PG) - 2026
Cell Biology
View Solution
Which Harappan site is famous for its sophisticated water management system and a stadium?
CUET (PG) - 2026
Ancient Civilization
View Solution
The light pink colour of \([Co(H_2O)_6]^{2+}\) and the deep blue colour of \([CoCl_4]^{2-}\) are due to:
CUET (PG) - 2026
Coordination chemistry
View Solution
View More Questions