To find the critical path, we first need to calculate the total durations for each possible path in the network and identify the longest path, which determines the project duration. Let's go step by step:
1. Path 1: \( 1 \to 2 \to 3 \to 6 \)
- Duration: \( A (3) + D (5) + G (6) = 3 + 5 + 6 = 14 \) days.
2. Path 2: \( 1 \to 4 \to 3 \to 6 \)
- Duration: \( A (3) + E (7) + D (5) + G (6) = 3 + 7 + 5 + 6 = 21 \) days.
3. Path 3: \( 1 \to 5 \to 6 \)
- Duration: \( A (3) + F (1) + G (6) = 3 + 1 + 6 = 10 \) days.
4. Path 4: \( 1 \to 4 \to 5 \to 6 \)
- Duration: \( A (3) + E (7) + F (1) + G (6) = 3 + 7 + 1 + 6 = 17 \) days.
Now, comparing the total durations, we find that Path 2, \( 1 \to 4 \to 3 \to 6 \), has the longest duration of 21 days, which means it is the critical path.
Thus, the critical path is \( 1 \to 4 \to 3 \to 6 \) and the correct answer is (B).