The ground condition where the tunnel roof typically needs immediate support after excavation and walls can only stand for a few minutes is called as

Show Hint

In tunnelling, ground is classified by how long it can stand unsupported (its stand-up time) after excavation. This guides how quickly support must be installed.
Updated On: Jun 16, 2026
  • Firm ground
  • Running ground
  • Soft ground
  • Self-supporting ground
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Concept:
In tunnelling, ground is classified by how long it can stand unsupported (its stand-up time) after excavation. This guides how quickly support must be installed.

Step 1:
Self-supporting and firm ground can stand for long periods without immediate support, while running ground flows out rapidly. These do not match the described behaviour.

Step 2:
Soft ground is the condition where the roof needs immediate support after excavation and the walls can stand only for a few minutes before failing. This short stand-up time defines soft ground.

Answer: Option (3) — Soft ground.