From the network diagram, the total float for an activity is the difference between the latest start time (LST) and the earliest start time (EST). We start by calculating the EST, EFT, LST, and LFT for each activity.
For Activity E:
- The duration of activity E is 4 days.
- The EST of E is 8 (calculated from the preceding activities).
- The EFT of E is \( EST + {duration of E} = 8 + 4 = 12 \).
- The LST of E is \( LST = LFT - {duration of E} = 13 - 4 = 9 \).
- The LFT of E is 13, which is the same as the LST of the following activity.
Now, the total float for activity E is:
\[
{Float} = LST - EST = 9 - 8 = 1
\]
Thus, the total float for activity E is 1 day.