Comprehension
The COVID-19 pandemic has taken the entire world hostage in less than four months, and the global economy has been hit the hardest with governments across the globe implementing stringent policies including lockdown to control the coronavirus outbreak. The pandemic today presents unprecedented challenges and impediments to businesses in conducting their normal operations. The lockdown across the world has caused delays in the performance of contracts and transactions. Now, the question that arises is whether the current situation can enable parties to a contract to alter their obligations with non-compliance of terms neither being regarded as a "default committed by any party" nor a "breach of contract"? There are certain well-accepted practices for dealing with such extraordinary situations in commercial transactions by the inclusion of force majeure & material adverse effect (MAE) clauses. Determination of the types of circumstances so covered by the force majeure clause contained in a contract is essential. Provisions of force majeure often cover natural disasters like hurricanes, floods, and earthquakes as "acts of God." Other covered events may include war, terrorism, civil disorder, fire, disease medical epidemics or by reasons of applicable laws or regulations. Broadly, the Courts have interpreted the term "Force Majeure" as an event that can neither be anticipated nor controlled by either of the contracting parties. A force majeure clause applies in the context of ongoing contractual arrangements, whereas, an MAE or material adverse change (MAC) clause applies to the allocation of risk in transactions before their closure or completion. Pandemic and related consequences such as government action is a type of event covered by a force majeure clause, however, its impact on the affected party's ability to perform its contractual obligations may vary depending upon contractual terms. It is common for force majeure clauses to specify the impact that the event or circumstances in question must have, in order for the clause to be triggered. References may be made, for example, to the event or circumstances having "prevented", "hindered" or "delayed" performance. These terms require different levels of impact on performance before a party can claim recourse to these clauses. In other words, the force majeure and MAC clauses act as an exception to what would otherwise be treated as a breach of contract. Certain contracts may state that, if a force majeure clause is applied, the contract may automatically be terminated. On the other hand, some contracts may even state that the duty to fulfil the contractual obligation may be suspended for a certain period of time and if the force majeure event is not curbed or treated even after such time, then eventually the contract may be terminated. Though there cannot be a one-size-fits-all solution to this question, and it depends upon how the force majeure clause is worded in a specific contract; and in the absence of the same, applicable laws related to the same will be required to be taken into consideration.
Question: 1

Based on the Author‘s argument in passage above, which of the following is correct ?

Updated On: Jul 15, 2026
  • Force Majeure Clauses, generally have a uniform impact on the performance of Contracts in all the cases.
  • The Impact on the performance of Contracts by the usage of Force Majeure Clauses is dependent upon the way such clauses have been constructed in a particular Contract.
  • Both Force Majeure and Material Adverse Change Clauses have similar impact on the performance of Contracts.
  • All of the above.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Approach Solution - 1

The correct option is (B) :The Impact on the performance of Contracts by the usage of Force Majeure Clauses is dependent upon the way such clauses have been constructed in a particular Contract.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

The question asks which statement correctly reflects the author's argument about how a Force Majeure clause affects the performance of a contract. Let's assess each option against that argument.

  1. Option A (uniform impact in all cases): This claims that Force Majeure clauses always produce the same effect on contract performance, regardless of contract. That cannot be right because a Force Majeure clause is a negotiated contractual term, not a statutory rule, so its effect changes with how each clause is drafted, what events it lists, and what relief it grants.
  2. Option B (impact depends on how the clause is drafted): This matches the author's point directly. Some Force Majeure clauses list only specific events like war or natural disaster, others use broad catch-all language, and some clauses excuse performance entirely while others only suspend it. Because the wording varies from contract to contract, the effect on performance also varies from contract to contract.
  3. Option C (Force Majeure and Material Adverse Change clauses have similar impact): This is incorrect. A Force Majeure clause excuses or suspends a party's performance because of an external event beyond its control, while a Material Adverse Change clause is used to assess whether a material change in a target's business, assets or financial condition allows a party to walk away from or renegotiate a transaction. These serve different purposes and operate differently, so they do not have a similar impact.
  4. Option D (all of the above): Since Option A and Option C are both incorrect, Option D cannot be correct either, because it depends on all three statements being true.

Only Option B correctly captures the author's argument: the impact of a Force Majeure clause on contract performance depends on the specific way that clause has been drafted in that particular contract.

Therefore, the correct answer is Option B: the impact on the performance of contracts by the usage of Force Majeure clauses is dependent upon the way such clauses have been constructed in a particular contract.

Was this answer helpful?
0
0
Question: 2

Imagine, there is a domestic commercial Contract for supply of certain goods for certain price between A and B. However, in pursuance of the same, both A and B forget to negotiate and agree on the terms of a Force Majeure event and the Contractual document does not contain the Force Majeure clause. In such a situation, what would be the fate of the Contract in the event like that of COVID 19 ?

Updated On: Jul 15, 2026
  • As the parties did not negotiate on the Force Majeure Clause, either of them cannot take an exception to the Breach of Contract.
  • The parties can invoke the Material Adverse Change Clause.
  • In absence of such clauses in the Contract, the Courts may resort to the applicable law, i.e., the Indian Contract Act, 1872 to give relief to the parties.
  • None of the above.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Approach Solution - 1

The correct option is (C) :In absence of such clauses in the Contract, the Courts may resort to the applicable law, i.e., the Indian Contract Act, 1872 to give relief to the parties.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

The question tests what happens when a contract has no Force Majeure clause at all and a supervening event like COVID-19 makes performance difficult. Let's look at each option.

  1. Option A (no exception can be taken to breach): This is incorrect. Indian contract law does not leave a party remedy-less just because the parties failed to negotiate a Force Majeure clause. The Indian Contract Act, 1872 has its own doctrine, under Section 56, that deals with contracts becoming impossible or unlawful to perform, so a party is not automatically in breach with no defense available.
  2. Option B (invoke the Material Adverse Change Clause): This is incorrect because the question already tells us that the parties did not negotiate any such clause into the contract. A Material Adverse Change clause, like a Force Majeure clause, only applies if it was actually written into the contract. It cannot be invoked if it was never agreed upon.
  3. Option C (courts may resort to the Indian Contract Act, 1872): This is correct. When a contract is silent on Force Majeure, Section 56 of the Indian Contract Act, 1872, which codifies the doctrine of frustration, becomes the fallback. Courts apply this statutory doctrine to decide whether the contract stands discharged or whether relief should be granted because performance has become impossible or radically different due to an unforeseen event.
  4. Option D (none of the above): This is incorrect since Option C is a valid and correct statement.

Since neither party inserted a Force Majeure or Material Adverse Change clause, the dispute falls back on general contract law, specifically the Indian Contract Act, 1872.

Therefore, the correct answer is Option C: in absence of such clauses in the contract, the courts may resort to the applicable law, i.e., the Indian Contract Act, 1872, to give relief to the parties.

Was this answer helpful?
0
0
Question: 3

In the same fact situation as mentioned above with a modification that there is a Force Majeure Clause in the Contract between A and B, let us suppose, that B, who was to supply goods to A on certain date and time, faced issues in relation to procurement of goods due to mill strike and also because of rise in prices of goods. In this case, can B claim the suspension of performance of Contract on the basis of the Force Majeure Clause ?

Updated On: Jul 15, 2026
  • Yes, B can, depending upon the way, the Force Majeure Clause is worded.
  • Such situation cannot be covered under Force Majeure as it is just a case of disappointed expectations and hence B cannot invoke the clause. It is merely a case of commercial hardship.
  • B can invoke the Force Majeure clause as the clause is too broad to cover such situations.
  • None of the above.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Approach Solution - 1

The correct option is (B) :Such situation cannot be covered under Force Majeure as it is just a case of disappointed expectations and hence B cannot invoke the clause. It is merely a case of commercial hardship.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

This question asks whether B can use the Force Majeure clause to suspend performance simply because procurement became harder and prices rose. Let's examine each option.

  1. Option A (yes, depending on wording): This looks attractive at first since Force Majeure clauses are interpreted according to their wording, but the facts given, a mill strike and a rise in prices, are ordinary commercial risks that a supplier is expected to absorb. Even a broadly worded Force Majeure clause is not read to cover routine business setbacks like these, so this option overstates B's position.
  2. Option B (cannot be covered, mere commercial hardship): This is correct. A strike affecting the supplier's own procurement and a rise in the price of goods are risks inherent in running a supply business. Courts treat this as a case of disappointed commercial expectations, not an event beyond the party's control that frustrates the contract, so B cannot use the Force Majeure clause to escape performance.
  3. Option C (B can invoke it as too broad): This is incorrect. Even a broadly drafted Force Majeure clause is still limited to genuinely unforeseeable events outside a party's control. It is not stretched to cover an increase in the cost of doing business, since that would let any party escape a bad bargain by calling it Force Majeure.
  4. Option D (none of the above): This is incorrect since Option B correctly answers the question.

A mill strike affecting the supplier and a rise in prices are business risks B is expected to bear, not events that excuse performance.

Therefore, the correct answer is Option B: such a situation cannot be covered under Force Majeure, as it is merely a case of commercial hardship.

Was this answer helpful?
0
0
Question: 4

Typically, the MAE (Material Adverse Change) provision in an agreement contemplates events which if they occur, or are likely occur, would have a “materially adverse change or effect on the assets, business, property, liabilities, financial condition, results, operations of the target” or that "affects the ability of the transacting parties to consummate the transaction" or the "validity or enforceability of the transacting parties to its rights and remedies under the transaction documents". Which of the following sample clauses in a contract resembles an MAE clause ?

Updated On: Jul 15, 2026
  • “In the event either party is unable to perform its obligations under the terms of this agreement because of Act of God, strikes, equipment of transmission failure or damage reasonably beyond its control, such party shall not be liable for damages to the other for any damages resulting from such failure to perform…”
  • “Except with respect to payment obligations under this agreement, no party shall be liable for, nor such party shall be considered in breach of this agreement due to, any failure to perform its obligations under this agreement as a result of cause beyond its control, including any earthquake, labour problem, unavailability of supplies…”
  • Both of the above.
  • None of the above.
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Approach Solution - 1

The correct option is (D) :None of the above.
Was this answer helpful?
0
0
Show Solution
collegedunia
Verified By Collegedunia

Approach Solution -2

The stem defines a Material Adverse Change (MAE) clause as one covering events that materially and adversely affect the assets, business, property, liabilities, financial condition, results or operations of the target, or that affect the ability to complete the transaction, or the validity and enforceability of the parties' rights. The question asks which of the two sample clauses matches that definition.

  1. Clause 1 (Act of God, strikes, equipment or transmission failure excusing liability): This clause excuses a party from liability for damages when it cannot perform because of events like an Act of God, strikes or equipment failure. This is the classic structure of a Force Majeure clause, which excuses non-performance due to an external event, not an MAE clause, which is about assessing a material change in the target's condition or the deal's viability.
  2. Clause 2 (no liability for failure to perform due to cause beyond control, including earthquake, labour problem, unavailability of supplies): This clause has the same structure as Clause 1, excusing a party from being considered in breach when it cannot perform due to causes beyond its control. This is also a Force Majeure clause, not an MAE clause, since it excuses performance rather than measuring a material adverse change in the business or the deal.
  3. Both of the above: Since neither Clause 1 nor Clause 2 is actually an MAE clause, this option is incorrect.
  4. None of the above: This is correct. Both sample clauses are Force Majeure clauses that excuse non-performance due to events beyond a party's control. Neither one addresses a material adverse effect on the target's assets, business, financial condition or the ability to consummate the transaction, so neither fits the MAE definition given.

Both clauses excuse a party from liability because of an external disruptive event, which is the hallmark of Force Majeure drafting, not the hallmark of an MAE clause.

Therefore, the correct answer is Option D: none of the above.

Was this answer helpful?
0
0

Top CLAT Questions

View More Questions