The question asks which statement correctly reflects the author's argument about how a Force Majeure clause affects the performance of a contract. Let's assess each option against that argument.
Only Option B correctly captures the author's argument: the impact of a Force Majeure clause on contract performance depends on the specific way that clause has been drafted in that particular contract.
Therefore, the correct answer is Option B: the impact on the performance of contracts by the usage of Force Majeure clauses is dependent upon the way such clauses have been constructed in a particular contract.
The question tests what happens when a contract has no Force Majeure clause at all and a supervening event like COVID-19 makes performance difficult. Let's look at each option.
Since neither party inserted a Force Majeure or Material Adverse Change clause, the dispute falls back on general contract law, specifically the Indian Contract Act, 1872.
Therefore, the correct answer is Option C: in absence of such clauses in the contract, the courts may resort to the applicable law, i.e., the Indian Contract Act, 1872, to give relief to the parties.
This question asks whether B can use the Force Majeure clause to suspend performance simply because procurement became harder and prices rose. Let's examine each option.
A mill strike affecting the supplier and a rise in prices are business risks B is expected to bear, not events that excuse performance.
Therefore, the correct answer is Option B: such a situation cannot be covered under Force Majeure, as it is merely a case of commercial hardship.
The stem defines a Material Adverse Change (MAE) clause as one covering events that materially and adversely affect the assets, business, property, liabilities, financial condition, results or operations of the target, or that affect the ability to complete the transaction, or the validity and enforceability of the parties' rights. The question asks which of the two sample clauses matches that definition.
Both clauses excuse a party from liability because of an external disruptive event, which is the hallmark of Force Majeure drafting, not the hallmark of an MAE clause.
Therefore, the correct answer is Option D: none of the above.