Question:

The correct order of series of operations to be carried out in production planning control is:

Show Hint

Remember the classic PPC acronym sequence: R-S-D-F (Routing $\rightarrow$ Scheduling $\rightarrow$ Dispatching $\rightarrow$ Follow up).
Updated On: Jul 4, 2026
  • Dispatching -- Routing -- Scheduling -- Follow up
  • Routing -- Scheduling -- Follow up -- Dispatching
  • Routing -- Scheduling -- Dispatching -- Follow up
  • Scheduling -- Routing -- Dispatching -- Follow up
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Concept: Production Planning and Control (PPC) coordinates the operational workflow of a manufacturing facility using four sequential phases:

Routing: Determines the optimal path, sequence of operations, and machines required to transform raw materials into a finished part. (Answers *Where* and *How*).

Scheduling: Assigns specific start and completion times for each operation. (Answers *When*).

Dispatching: Issues official production orders and releases the work packages to the factory floor to initiate real-time operations. (Answers *Action*).

Follow up (Expediting): Monitors active production progress against the plan to catch bottlenecks and fix delays. (Answers *Verification*).

Step 1: Establish the logical sequence of operations. - A factory must plan the operational path before assigning execution times: $\text{Routing} \rightarrow \text{Scheduling}$. - Timelines must be finalized before authorizing the shop floor to begin work: $\text{Scheduling} \rightarrow \text{Dispatching}$. - Monitoring and expediting can only occur after the work has been dispatched and initiated: $\text{Dispatching} \rightarrow \text{Follow up}$. Therefore, the correct operational sequence is: Routing $\rightarrow$ Scheduling $\rightarrow$ Dispatching $\rightarrow$ Follow up.