Step 1: Recall the definition of the critical path.
The critical path is the sequence of activities that determines the minimum completion time of the project.
Step 2: State its characteristic.
It is the path having
\[
\boxed{\text{the longest total duration}}
\]
and zero total float.
Hence,
\[
\boxed{(A)}
\]
is the correct answer.