Question:

In network analysis using the Critical Path Method (CPM), the critical path is the one with

Show Hint

Critical path characteristics: \[ \boxed{ \text{Longest Duration} \quad\text{and}\quad \text{Zero Float}. } \]
Updated On: Jul 14, 2026
  • The longest duration
  • Total float
  • Maximum resources
  • Negative float
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Recall the definition of the critical path. The critical path is the sequence of activities that determines the minimum completion time of the project.

Step 2:
State its characteristic. It is the path having \[ \boxed{\text{the longest total duration}} \] and zero total float. Hence, \[ \boxed{(A)} \] is the correct answer.