Question:

In critical path method, critical path moves along with the activities having total float of:

Show Hint

The critical path in a project has zero float, indicating that any delay in these activities will delay the project completion.
Updated On: May 22, 2025
  • Positive value
  • Same value
  • Zero value
  • Negative value
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Understanding critical path.
In the Critical Path Method (CPM), the critical path is the longest path in the project schedule. It determines the minimum time required to complete the project.
Step 2: Activities with zero float.
The critical path consists of activities that have zero total float, meaning there is no room for delay. Any delay in these activities will directly result in a delay of the entire project.
Was this answer helpful?
0
0