Question:

In a PERT network, the time estimate of an activity is as per the following: Optimistic time is \(4\) days, most likely time is \(6\) days and pessimistic time is \(14\) days. The expected time and standard deviation of the activity (in days) are respectively

Show Hint

PERT formulas: \[ \boxed{ t_e=\frac{a+4m+b}{6} } \] \[ \boxed{ \sigma=\frac{b-a}{6} } \] \[ \boxed{ \text{Variance}=\sigma^2=\left(\frac{b-a}{6}\right)^2 } \]
Updated On: Jul 14, 2026
  • \(6.0\) & \(2.76\)
  • \(6.0\) & \(3.78\)
  • \(7.0\) & \(1.67\)
  • \(7.0\) & \(2.76\)
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Use the PERT expected time formula. The expected time is \[ t_e=\frac{a+4m+b}{6}, \] where \[ a=4,\qquad m=6,\qquad b=14. \] Thus, \[ t_e = \frac{4+4(6)+14}{6} = \frac{42}{6} = 7\ \text{days}. \]

Step 2:
Calculate the standard deviation. The standard deviation is \[ \sigma=\frac{b-a}{6}. \] Therefore, \[ \sigma = \frac{14-4}{6} = \frac{10}{6} = 1.67\ \text{days}. \] Hence, \[ \boxed{t_e=7.0\ \text{days},\qquad \sigma=1.67\ \text{days}} \] is the correct answer. Therefore, \[ \boxed{(C)} \] is the correct answer.
Was this answer helpful?
0
0