Question:

In a cut-and-fill stope, the main purpose of backfilling is to

Show Hint

Backfilling mainly provides \[ \boxed{ \text{Ground support and wall stability.} } \]
Updated On: Jul 14, 2026
  • Reduce ore dilution
  • Prevent high stress concentrations in far field domain
  • Prevent displacement due to dilation of fractured wall rock
  • Improve ore rehandling
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Recall the purpose of backfilling. In cut-and-fill stoping, the excavated void is filled with waste material after ore extraction.

Step 2:
State the primary function. Backfill provides support to the surrounding rock mass and prevents movement caused by dilation of fractured wall rocks. Hence, \[ \boxed{\text{Prevent displacement due to dilation of fractured wall rock}.} \] Therefore, \[ \boxed{(C)} \] is the correct answer.
Was this answer helpful?