Question:

If two projects have the same PVB but Project A has a higher IRR than Project B, what is the usual recommendation when capital is limited?

Show Hint

For capital-constrained projects, \[ \boxed{ \text{Higher IRR} \Rightarrow \text{Higher return per unit investment}. } \]
Updated On: Jul 14, 2026
  • Choose the project with the higher NPV regardless of IRR
  • Choose the project with the higher IRR
  • Always choose the project with a longer life
  • Reject both projects
Show Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Recall the significance of IRR. The Internal Rate of Return (IRR) represents the discount rate at which the Net Present Value (NPV) of a project becomes zero.

Step 2:
Select the preferred project. When competing projects have the same present value of benefits (PVB) and capital is limited, the project with the higher IRR generally provides a better return on investment. Hence, \[ \boxed{\text{Choose the project with the higher IRR}.} \] Therefore, \[ \boxed{(B)} \] is the correct answer.
Was this answer helpful?
0
0